Current status of ZGM's investment activities
Two cranes are currently standing in Zell-Barl. In April Zimmermann-Graeff & Müller (ZGM) announced the beginning of various construction activities with a total volume of 25 million euros. The first results can be recognized.
The earthworks for the new high-bay warehouse as well as for the despatch and commissioning hall were completed, a fundament was built. Now, next to the administrative building which was completed in 2011, the first racks can be seen. "The new high-bay warehouse will be completed in March 2017 so that we can integrate it into the production processes in September of the same year," says Dr. Tina Schiemann, Managing Director of ZGM for Logistics, Production, Planning and Operations.